Raise the lift arms and install an approved lift arm support device. (See Installing on Page 10-20-1.)
Raise the operator cab. (See Raising on Page 10-30-2.)
Remove the lift arm bypass control knob and rubber washer (Item 1) [Figure 50-101-1].
Remove the bolts from the speed control bracket (Item 2) [Figure 50-101-1].
Installation: Tighten the screws to 15 – 20 ft.-lb. (20 – 27 N•m) torque.
Remove the bolts from the speed control lever (Item 3) [Figure 50-101-1].
Installation: Tighten the two screws evenly until the speed control lever moves back and forth at a comfortable tension.
Remove the fuse/relay cover mount screws (Item 1) [Figure 50-101-2]. Remove the cover.
Installation: Tighten the screws to 8 – 11 ft.-lb. (11 – 15 N•m) torque.
Remove the fuse/relay shield mounting screws (Item 3) [Figure 50-101-2]. Remove the shield.
Installation: Tighten the screws to 15 – 20 ft.-lb. (20 – 27 N•m) torque.
Remove the control panel mount screws (Item 1) [Figure 50-101-3] from the both sides of the control panel.
Installation: Tighten the control panel mounting screws to 15 – 20 ft.-lb. (20 – 27 N•m) torque.
Disconnect the right and left joystick wire harness connectors (Item 1) [Figure 50-101-4].
Remove the control panel from the loader.
Remove the three bolts from the SJC controller mounting plate to lower the controller when removing the control panel.